What Is Vendor Inspection? Roles & Responsibilities

What Is Vendor Inspection? Roles & Responsibilities
What Is Vendor Inspection? Roles & Responsibilities

Vendor inspection is the buyer’s QA/QC at the supplier’s works to verify materials and equipment against the PO, drawings, and referenced standards. It covers ITP/QCP review, staged in-process checks, witness/hold points, FAT, and documentation. Inspectors collect objective evidence and accept/reject strictly per API/ASME/ISO/EN referenced by the project spec.

 

 

Vendor Inspection — Plain Definition (clear & practical)

Vendor inspection (a.k.a. supplier or source inspection) is product/job-focused QA/QC performed at the manufacturer or sub-vendor to confirm conformity before shipment. It aligns the ITP (Inspection & Test Plan), witness/hold points, and acceptance “as per API/ASME/ISO/EN referenced by the project spec.”

Where it happens

  • Supplier’s fabrication/assembly line
  • Sub-vendor special processes (e.g., heat treatment, coatings, NDE)
  • Factory Acceptance Testing (FAT) bays and certified test labs

Scope vs. vendor audit

  • Inspection = does this item/job meet PO/drawings/ITP and the referenced standard?
  • Audit = does the quality management system meet ISO 9001 or buyer requirements?

 

Why Vendor Inspection Matters (outcomes, not fluff)

  • Prevents cost & delay: catches nonconformities before shipment/site works.
  • Compliance by design: acceptance is applied per the cited clauses (no ad-hoc limits).
  • Traceability you can trust: MTCs, calibrated instruments, tagged photos, IRs/NCRs tied to serials.
  • Risk-based visibility: right witness vs hold points at the right stages.
  • Smoother FAT & release: clean dossiers, reduce punch lists and disputes.

 

TPI vs. In-House Inspector (quick rule-of-thumb)

  • Third-Party Inspection (TPI): independent assurance for high-risk/critical equipment, remote vendors, or when buyer bandwidth is limited.
  • In-house/buyer’s inspector: when deep product knowledge or close coordination with engineering is key.
    Either way, acceptance remains per the project-referenced API/ASME/ISO/EN.

 

Roles & Responsibilities in Vendor Inspection (RACI)

Goal: remove ambiguity. Every task has one Accountable, clear Responsible parties, and informed C/I stakeholders. Acceptance is always per API/ASME/ISO/EN referenced by the project spec.

RACI Matrix (example — adapt to your PO)

Task / Deliverable Buyer/Owner QA EPC / SQE Manufacturer QA/QC TPI End User/Ops
Prepare QCP/ITP C C R C I
Approve ITP & W/H points A C C C I
Notify visits (1–2 wks) C R R R I
Document screen (PO, dwgs, MTCs, cal certs) A R R C I
In-process surveillance A C R R I
Special processes (weld/HT/coat/NDE) A C R R I
FAT execution & records A C R R I
Issue IR (inspection report) A C R R I
Raise/close NCR A C R R I
Gauge/instrument calibration control I C R C I
Final dossier compilation A C R C I
Release note/shipping clearance A C R C I

Need a working ITP? Grab the vendor inspection ITP template to align tasks, witness/hold points, and records.

 

Buyer/Owner QA/QC — Accountability & Acceptance

  • Owns acceptance: applies criteria as per referenced standards in the PO/ITP.
  • Approves ITP/QCP; defines W/H points and evidence required.
  • Reviews/approves deviations/concessions; signs release.
  • Ensures traceability (tags/serials), calibration policy, and dossier completeness.

Manufacturer QA/QC — Execution & Evidence

  • Prepares QCP/ITP; controls fabrication, special processes, and sub-vendors.
  • Ensures calibrated instruments, qualified procedures/personnel.
  • Runs FAT to approved procedures; compiles IRs, charts, MTCs, certificates, photos.
  • Delivers a clean final dossier mapped to item/tag and ITP.

Third-Party Inspection (TPI) — Independent Verification

  • Performs surveillance to the approved ITP; witnesses W/H points.
  • Issues IRs with objective facts (readings, clause refs, instrument IDs).
  • Raises NCRs when acceptance isn’t met; verifies corrections/re-tests.
  • Maintains independence; reports to the buyer/owner.

EPC / Supplier Quality Engineering — Coordination

  • Aligns schedule, readiness, and notifications; ensures sub-vendor coverage.
  • Tracks actions from IR/NCR to closure; keeps stakeholders C/I as agreed.
  • Checks that procedures cite the correct standard/edition.

End User / Operations — Service Criticality

  • Provides service-critical requirements (e.g., shutdown impacts, operability checks).
  • May witness FAT for function/controls; remains Informed on quality status.

 

Handover Essentials (don’t skip these)

  • Before first visit: approved ITP/QCP, latest drawings/datasheets, referenced standards list, test procedures, calibration status.
  • At FAT start: readiness sheet, tag/serial list, gauge IDs and valid cal certs, safety permits.
  • At release: signed IRs, NCR log (closed), test charts, MTCs/CoC, NDE reports, photos, release note—all per project spec.

 

The Vendor Inspection Process (PO → Release)

Step 1 — Contract Inputs & Kick-off

  • Gather baselines: PO, datasheets, drawings/BOM, manufacturing schedule, sub-vendor list.
  • List referenced standards: API/ASME/ISO/EN as named in the project spec (no ad-hoc criteria).
  • Draft QCP/ITP: define stages, witness (W) and hold (H) points, objective evidence required.
  • Comms & notifications: who invites whom, lead-times (e.g., 7–14 days), site safety/permits.

Need a structured starter? Use the vendor inspection ITP template to align W/H points and records.

 

Step 2 — ITP/QCP Review & Approval

Align the ITP with risk, schedule, and acceptance per the standards referenced by the project spec.

ITP Review Checklist (paste into your doc)

Item Reference Acceptance reference Status Action owner
Latest drawings/datasheets listed PO / doc register Per order
Each stage has W/H point defined ITP §… Per project spec
Test procedures cite correct standard/edition Procedures Per referenced standard
Records required (charts, MTCs, cal certs, photos) ITP §… Per project spec
Sub-vendor controls included QCP §… Per project spec

 

Step 3 — In-Process Surveillance & Special Processes

Monitor manufacturing and special processes; apply acceptance per the cited clauses (welding, heat-treat, coating, NDE).

Stage Control Plan (example)

Stage Key checks Acceptance reference Records
Casting/forging receipt ID/qty, condition, certs Per order & referenced standard IR, photos
Welding & WPS/PQR Welder quals, parameters Per ASME IX/ISO welding as referenced Logs, WQRs
Heat treatment Cycle, soak, charts Per project spec/standard HT chart, IR
Coating/lining DFT, cure, holiday test Per project coating spec DFT log, photos
Dimensional checks F2F, flanges, interfaces Per drawings/standard Sheet, IR

Reduce repeat NCRs with preventive controls and staging—see prevent vendor nonconformities.

 

Step 4 — FAT (Factory Acceptance Testing)

Run functional/performance tests to approved procedures; instruments must be calibrated and traceable.

FAT Readiness Checklist

Item Status Evidence
Approved procedures on bench Rev/date
Gauge/recorder cal certs valid Cert IDs
Tag/serial list printed List v…
Safety permits (LOTO, pressure) Permit IDs
Witness roster confirmed Emails

During FAT

  • Record readings, instrument IDs, and photo IDs.
  • Acceptance is per API/ASME/ISO/EN referenced by the project spec (do not invent values).
  • Log deviations immediately; contain, correct, re-test.

 

Step 5 — Dossier & Release

Compile objective evidence; map every record to item/tag.

Final Dossier Index (starter)

Section Contents Acceptance reference Signatures
Admin PO, datasheet, drawings Per order Buyer/Vendor
ITP/QCP Approved copies, W/H log Per project spec Buyer
Material MTCs, trace map Per referenced standard Vendor
Process Welding/HT/Coating records Per referenced standard Vendor/Inspector
Tests FAT charts, setpoints Per referenced standard Inspector
NDE Reports, maps Per referenced standard Level II/III
NCRs Log, dispositions Per procedure Buyer
Photos Tagged, dated Per project spec
Release IRs, release note Per order Buyer

 

Witness & Hold Points (How to Set Them)

Typical W/H Map (risk-based)

Stage Risk rationale W/H Acceptance reference Required records
First-article dimensional Fit-up risk W Per drawings/standard Dim sheet, IR
Weld procedure/qualification Pressure boundary H Per welding standard referenced WPS/PQR/WQR
Heat treatment cycle Mechanical props W Per project spec/standard HT chart
NDE on critical welds Hidden defects W Per NDE standard referenced NDE report/map
Performance/FAT Function & safety H Per API/ASME/ISO/EN referenced Charts, photos
Final inspection & dossier Shipment readiness H Per order/spec Signed index, release

Practical tips

  • Tie W/H to highest risk and irreversible steps.
  • Define prerequisites (e.g., “Do not proceed to FAT until cal certs verified”).
  • Set notification windows and alternates to avoid slips.
  • Use clear pass/fail language: “Acceptance as per clause X of the referenced standard.”

Vendor Inspection Standards & Acceptance (placeholders, no numbers)

Rule: do not invent values. Apply acceptance as per API/ASME/ISO/EN referenced by the project spec and the edition named in the PO/ITP.

Quick Reference Map (use only if referenced by your project)

Area Common standard (if applicable) How it’s used in vendor inspection
Pressure/functional tests (valves/packages) API 598; ISO 5208; EN 12266-1/2 Tightness/shell tests at FAT per referenced clauses
Pressure equipment design/tests ASME VIII / EN 13445 (where applicable) Hydro/ pneumatic tests per spec; dossier evidence
Piping/fabrication ASME B31.x / EN piping codes Dimensional/NDE per referenced sections
Dimensions & flanges ASME/EN B16 series (as named) Face-to-face, bolt circles per drawings/standard
Welding & brazing ASME IX / ISO 15614/9606 WPS/PQR/WQR per referenced welding code
NDE methods ASME V / ISO 17635 et al. PT/MT/UT/RT extent & acceptance per project
Materials & MTCs EN 10204 (cert types) Trace heats to tags/serials; certificate validity
Coating/lining Project coating spec; ISO series (as named) DFT/holiday/cure checks per spec
Calibration & labs Project calibration procedure; ISO/IEC 17025 (labs) Valid cal certs matched to instrument IDs

Always cite: “Acceptance per <standard/edition> referenced by the project spec.” Do not restate numeric limits.

 

Examples & Templates (copy/paste into your program)

Vendor Inspection IR (Inspection Report) — Field Set

Field What to record
Supplier / Location Works, bay, sub-vendor if any
PO / Item / Tag-Serial Exact identifiers (match to dossier)
Stage / W/H point From approved ITP
Procedure & Standard reference Doc IDs + clause/edition as referenced
Instruments IDs + valid calibration
Observations Measured values, photos (IDs), defects
Result Conform / NCR raised
Attachments Charts, MTCs, NDE, photos
Inspector & Buyer Names, signatures/date

NCR Workflow (practical, fast)

  1. Contain: stop use/ship; mark item/tag.
  2. Correct: repair/rework per approved procedure & standard reference.
  3. Verify: re-inspect/re-test; record clause and readings.
  4. Concession (if needed): buyer QA approves or rejects.
  5. Close: update dossier; prevent recurrence (link to CAPA).

Release Readiness Checklist

  • Approved ITP/QCP; all W/H signed.
  • IRs, charts, NDE, MTCs/CoC mapped to tags/serials.
  • Calibration certificates current and referenced in reports.
  • Deviations/NCRs closed or concession approved by buyer.
  • Final dossier index signed; release note issued.

 

When the Item Is a Valve

Inspecting valves? Use our dedicated, step-by-step guide: Valve Inspection Checklist — visual/markings, dimensional, materials/traceability, and pressure/functional tests with placeholders as per API 598 / ISO 5208 / EN 12266 referenced by your project.

 

FAQs — Vendor Inspection

What is vendor inspection?
Buyer’s QA/QC at the supplier to verify conformity to the PO/drawings and referenced standards via ITP-driven checks, W/H points, FAT, and documentation.

Who prepares and who approves the ITP?
The manufacturer prepares; buyer/owner QA approves. TPI may review. Acceptance follows the standard/edition referenced by the project.

What’s the difference between expediting and inspection?
Expediting drives schedule/readiness; inspection verifies quality and acceptance per standards.

Are witness and hold points mandatory?
Where the ITP defines them and the buyer requires them. Use W for visibility, H where irreversible risk exists.

Which standards apply to vendor inspection?
Only those named in the project spec/PO (e.g., API/ASME/ISO/EN). Apply acceptance per the cited clauses—don’t invent limits.

What must be in a final supplier dossier?
Approved drawings/ITP, IRs, test charts, MTCs/CoC, NDE, certificates, photos, deviations/waivers, and release note—as required by the order.

Who raises and who closes NCRs?
Inspector (buyer/TPI) can raise; the buyer/owner approves concession/closure after verified correction.

Can TPI replace in-house inspection?
TPI adds independence; use for high-risk items or vendor locations. Acceptance remains per project-referenced standards.

 

Download: Sample ITP & IR Forms (ZIP)

Filename: Sample_ITP_IR_Forms.zip

  • Editable ITP template with W/H points and acceptance placeholders per referenced standards.
  • Inspection Report (IR) form + NCR register to track findings and dispositions.
  • Final dossier index to standardize evidence and speed release.

CTA: Download the Sample ITP & IR Forms (ZIP) and start your vendor inspection program today.

 

Vendor Inspection Training — Upskill Your Team

Want structured practice and real checklists? Join Vendor Inspection Training — plan ITPs, set witness/hold points, run FATs, and apply acceptance as per the standards your projects reference.

 

Vendor Inspection vs Expediting vs Audit (clear comparison)

Topic Vendor Inspection Expediting Vendor Audit
Primary aim Verify product/job quality against PO/drawings and referenced standards Drive schedule/readiness, materials on time Assess QMS/system capability
Evidence Measurements, charts, IR/NCR, photos, tag/serial traceability Milestones, dates, material arrival, manpower Procedures, records, internal audits
Tools ITP/QCP, witness/hold points, FAT Look-ahead plan, risk log, recovery plan Checklist vs ISO 9001 or buyer criteria
Acceptance Per API/ASME/ISO/EN referenced by project spec N/A (schedule metrics) Conformance to system requirements
Outcome Release note / ship-clearance (or NCR) Schedule recovery actions Audit report & CAPA
Who leads Buyer QA/QC / TPI Project controls / expeditor Supplier quality / buyer audit team

 

Email Templates (plug-and-play)

1) Vendor Inspection Notification (W/H point)

Subject: Inspection Notification — PO [####], Item/Tag [####], [W/H] at [Vendor, City] on [Date]

Hello Team,
As per the approved ITP, we plan the [Witness/Hold] for [Stage: e.g., FAT / NDE / Dimensional] on [Date, Time, Timezone] at [Vendor, Address].

References: PO [####], Drawing/Datasheet [IDs], Procedure [ID/Rev], standard/edition as referenced by project spec.
Readiness: procedures at bench, tag/serial list, valid calibration certificates for instruments to be used.
Please confirm attendance or share alternates.

Regards,
[Name], Buyer QA/QC

2) FAT Agenda & Readiness Check

Subject: FAT Agenda — PO [####], Package/Valve [####], [Dates]

Attached: FAT steps, hold/witness points, instrument IDs & cal certs, safety permits.
Acceptance will be applied as per API/ASME/ISO/EN referenced by the project spec.
Kindly acknowledge readiness and provide any constraints 48h prior.

— [Name], Supplier Quality

 

Inspection Report (IR) — worked example (concise)

  • Supplier / Location: Acme Valves, Bay 3 (Sub-vendor: Seat Overlay Ltd.)
  • PO / Item / Tag-Serial: PO 450123 / Gate Valve DN150 / GV-0150-A01
  • Stage / W/H: FAT — Hold (H)
  • Procedure & Standard Ref: FAT-VAL-012 Rev.2; acceptance per API 598 (edition per project spec)
  • Instruments: Pressure gauge G-245 (cal valid), Recorder R-009 (cal valid)
  • Observations: Hydrostatic shell test run; stabilization achieved; no visible leakage; seat leak test per procedure; readings attached (Charts C-112 to C-114).
  • Result: Conformant to referenced clauses; No NCR
  • Attachments: Charts C-112…C-114; photos P-021…P-030; tag map; cal certs list
  • Inspector / Buyer: J. Smith (TPI) / A. Novak (Buyer QA)

(Note: no numbers quoted; acceptance tied to the standard referenced by the project.)

 

One-Page Pocket Checklist (on-site use)

Before you start

  • Approved ITP/QCP on the table; correct standard/edition listed.
  • Latest drawings/datasheets; tag/serial list printed.
  • Calibration certificates valid and mapped to instruments.

Sequence

  1. Documentation screen (PO, procedures, MTCs, cal certs).
  2. Visual/markings (nameplate, size/class/material, preservation).
  3. Dimensional (F2F, flanges/threads, interfaces) — acceptance per drawings/standard.
  4. Materials & traceability (MTCs; PMI/hardness if specified).
  5. NDE (if required) — extent/acceptance per referenced clauses.
  6. FAT (hydrostatic, seat leak, functional) — as per API/ASME/ISO/EN referenced by project.
  7. Close-out (IR, NCR if any, charts, photos, final dossier index, release note).

Golden rules

  • Record facts (values, IDs, photos), not opinions.
  • Never choose ad-hoc leakage categories or hold times; use the referenced standard.
  • Every record maps to one tag/serial.

 

Where to Go Next (one click each)

  • Build your plan: Vendor Inspection ITP Template
  • Avoid repeat findings: Prevent Vendor Nonconformities
  • If your item is a valve: Valve Inspection Checklist

Training for your team?
Enroll in Vendor Inspection Training — plan ITPs, set witness/hold points, run FATs, and apply acceptance as per the standards your projects reference.