Quick Summary — Valve Inspection Checklist (for Featured Snippet):
A valve inspection checklist is a practical sequence for documentation, visual/markings, dimensional checks, materials/traceability, NDE (if required), and pressure/functional tests. Record measured results and apply acceptance exactly as referenced by your project spec (e.g., API 598, ISO 5208, EN 12266). Use it to streamline witness points and release.
How to Use This Valve Inspection Checklist
Use this valve inspection checklist at vendor FAT, incoming/receipt inspection, or pre-install checks. It is written for QA/QC managers, supplier quality engineers, and freelance inspectors.
- Confirm inputs: PO, datasheet, drawings/BOM, ITP/QCP, referenced standards (API/ASME/ISO/EN), approved test procedures, calibration certificates.
- Plan witness/hold points per ITP. Note which tests you will witness vs. review.
- Work in sequence: documentation → visual/markings → dimensional → materials/traceability → NDE (if specified) → pressure & functional tests.
- Record facts, not opinions: measured values, clause references, photo IDs, gauge tags.
- Apply acceptance exactly as referenced by the project spec (e.g., “per API 598/ISO 5208/EN 12266-1” in the procedure).
- Close out properly: punch list, NCRs/dispositions, sign-off, and release note.
- File everything in the valve dossier: signed checklist, calibrated charts, certificates, photos, and concessions.
Download the printable Valve Inspection Checklist (PDF) at the end of this article.
Pre-Inspection Documentation Review (foundation of your valve QC checklist)
A strong documentation screen prevents most downstream findings. This section of the valve inspection checklist ensures paperwork is complete, current, and traceable.
Required documents to have on the table
- Purchase Order, datasheet, approved drawings/BOM (latest rev)
- ITP/QCP with defined witness/hold points
- Test procedures referencing the governing standard (e.g., API 598 / ISO 5208 / EN 12266-1)
- Calibration certificates for gauges/recorders used in hydrostatic and seat leak tests
- Material Test Certificates (MTCs), Certificates of Conformity, heat/serial lists
- Previous deviations/NCRs and approved concessions (if any)
Acceptance criteria (apply what your spec references)
- Document completeness and revision status per project procedure
- Procedures cite the correct standard and edition as required by the PO/ITP
- Calibration certificates valid and traceable to instruments that will be used
- MTCs traceable to heat numbers and components listed on drawings/BOM
- Any open NCR/deviation has an approved disposition before tests proceed
Document Check Log (example)
| Document | Rev/Date | Standard/Spec Ref | Status (OK/Missing) | Remarks / Action Owner |
| Datasheet & GA drawing | C / 2025-07-15 | PO 450123; project spec §… | OK | — |
| ITP/QCP | 2 / 2025-07-10 | ITP VP-001; witness points | OK | Shell/seat tests “W” |
| Hydrostatic test procedure | 1 / 2025-07-10 | per API 598 / EN 12266-1 | OK | Gauge IDs listed |
| Seat leak (air/water) procedure | 1 / 2025-07-10 | per ISO 5208 | OK | Category to be confirmed |
| Calibration certs (gauges/rec.) | — | per project calibration control | MISSING | Vendor to upload before FAT |
| MTCs & heat/serial list | — | BOM; per order | OK | Heats cross-check in Materials section |
Visual Inspection & Markings (quick, high-value checks)
Goal: Catch obvious nonconformities before you invest time in pressure tests. This part of the valve inspection checklist focuses on visible condition, marking and nameplate checks, coatings/preservation, and documentation of defects.
External condition (visual inspection of valves)
- Body/bonnet: casting/forging integrity; no cracks, dents, arc strikes, or weld spatter.
- Sealing surfaces: no nicks, burrs, corrosion, or coating on seat faces.
- Threads/end prep: clean, correct form, protective caps/plugs installed.
- Internals (when accessible): debris-free; seat/ball/disc/gate undamaged.
- Operator/gear/actuator: mounting secure; travel stops set; indicator present.
- Preservation: rust inhibitor where specified; ends sealed; desiccants if required.
Acceptance: Per drawing and the standard referenced by the project spec.
Markings & nameplate check
Verify manufacturer, size, pressure class, material grade, trim, flow direction, tag/serial, and heat/heat code (where required) are present, legible, and match the order/datasheet. Cross-check tag numbers to test charts and the release documents.
Acceptance: Per order/drawing and applicable marking clauses in the referenced standard.
Coatings & DFT (if applicable)
Confirm coating/lining type, batch reports, curing notes, and dry film thickness at sample points (do not state numeric criteria; reference the project coating spec).
Visual & Marking Checklist (pass/fail log)
| Item | Requirement Ref (drawing/standard) | Observed | Photo/ID | Result (Pass/Fail) | Action Owner/Deadline |
| Body/bonnet surfaces | Order; visual criteria per project spec | Clean, no damage | IMG_112 | Pass | — |
| Seat faces clean | Procedure §… | No coating/burrs | IMG_115 | Pass | — |
| End protection | PO clause §… | Caps installed | IMG_117 | Pass | — |
| Nameplate data | Drawing MD-001 | All fields match | IMG_121 | Fail | Vendor to replace plate |
| Flow arrow present | Standard marking clause | Present, correct | IMG_122 | Pass | — |
Tip: attach defect photos with labels (arrow + part name) to speed review and NCR disposition.
Dimensional Verification (measure what matters)
Goal: Confirm fit-up with mating piping/equipment. Keep it efficient: measure critical features, record values, and cite the acceptance reference (drawing/ASME/EN) rather than rewriting tolerances.
What to measure (dimensional inspection of valves)
- Face-to-face / End-to-end length
- Flange geometry (OD, bolt circle, hole qty/size, raised face)
- Threaded ends (type, size, pitch, taper) or weld ends (bevel, land)
- Bore/port and any reduced/full-port requirement
- Stem/packing box dimensions, actuator interface, keyway/square
- Auxiliary ports (drains/vents/test connections) where specified
Tools & references
Use calibrated calipers, micrometers, depth gauges, thread gauges, and templates.
Acceptance is per drawing and the dimensional standard referenced by the project (e.g., ASME B16.34, B16.10/B16.5 as applicable).
Dimensional Check Sheet (example)
| Feature | Drawing Ref | Required | Measured | Acceptance Ref | Result |
| Face-to-face (DN100) | D-201 §A | — | 229.9 mm | Drawing D-201; per referenced standard | Pass |
| Flange BCD | D-201 §B | — | 180.1 mm | Drawing D-201; per referenced standard | Pass |
| Raised face height | D-201 §C | — | — | Project spec coating note
As per the referenced standard e.g. ASME B 16.5 |
Pass |
| Thread type (NPT/BSPT) | D-201 §D | NPT | NPT verified | Drawing D-201 | Pass |
| Bore | D-201 §E | Full port | Ø99.8 | Drawing D-201 | Pass |
Don’t copy tolerances into the sheet; instead, cite the clause or drawing that governs acceptance.
Material Verification & Traceability (MTCs, PMI, hardness)
Goal: Ensure the installed materials match the order and risk profile. This section of the valve QC checklist covers MTC review, PMI/hardness when required, and full heat/serial traceability.
MTC review (how to read valve MTCs)
- Check grade, product form, heat number, melt practice, and any impact/sour notes against the BOM/datasheet.
- Match heat/serials on body/bonnet/trim to the MTC list (where stamping or tagging is required).
- Confirm MTCs are certified and edition-aligned with the project spec.
Need a refresher? See our MTC interpretation guide.
PMI/Hardness (if specified by the project)
- Define locations/extent (e.g., body, bonnet, weld overlays, trim) in the ITP.
- Use calibrated instruments and approved procedures; acceptance per project spec and the standard it references.
- Record method, instrument ID, readings, location map, and disposition of any outliers.
Material & PMI Log (template)
| Component | Tag/Serial | Heat No. | MTC Ref | PMI/Hardness Result | Acceptance Reference | Status |
| Body (WCB) | VLV-1001 | H12345 | MTC-WCB-07 | PMI OK | Per order & referenced standard | Pass |
| Trim (13Cr) | VLV-1001 | T67890 | MTC-TRIM-13Cr | PMI OK | Per order & referenced standard | Pass |
| Overlay (if any) | — | — | — | Hardness pending | Project sour note §… | Hold |
Traceability rule of thumb: every reading, photo, and chart must map back to one valve tag/serial.
NDE (If Required by the Project Spec)
Purpose: Confirm surface and volumetric integrity where risk or code requires it. Extent and acceptance must follow the standard referenced by your project spec.
Methods & typical use
- VT (visual testing): always; surface condition, welds, seat faces.
- PT/MT: sealing surfaces, repair welds, hardfacing, stem welds.
- UT/RT: production or repair welds; critical sections where specified.
- Hardness mapping / ferrite (if applicable): sour service or overlay controls.
Acceptance: Per the procedure and clause cited by the project spec.
NDE Checklist (log template)
| Component/Area | Method | Procedure Ref | Extent | Indications | Disposition | Acceptance Ref | Result |
| Body-to-bonnet weld | MT | NDE-MT-012 | 100% | None | — | Per referenced standard | Pass |
| Seat overlay | PT | NDE-PT-021 | 100% | 1 linear | Blend & re-test | Per referenced standard | Closed/Pass |
Tip: add a simple indication map (sketch or photo with coordinates) to speed NCR review.
Pressure & Functional Tests (core of the valve inspection checklist)
All test parameters and acceptance must be as per the standard named in your PO/ITP (e.g., API 598, ISO 5208, EN 12266-1) and any project-specific overrides.
Hydrostatic Shell Test (pressure boundary)
- Media & temperature, pressurization, hold: run per approved procedure; gauge/recorder calibration verified.
- Monitoring: leakage, sweating, body/bonnet joints, test blinds, taps.
- Acceptance: Per API 598 / ISO 5208 / EN 12266-1 referenced by the project spec.
- Want a refresher on method differences? See the hydrostatic vs seat leak test.
Seat Leak Test (tightness)
- Direction(s): with/against flow as specified; single or double isolation seats.
- DP/Category: apply exactly what your procedure cites (no ad-hoc categories).
- Media: air/gas or water as specified; stabilization time recorded.
- Acceptance: Per the standard referenced, e.g., categories/rates as per API 598 or ISO 5208.
- Compare frameworks here: API 598 vs ISO 5208.
Functional Checks (operability & accessories)
- Actuation/torque: smooth travel, no binding; verify gear/actuator settings.
- Position indication & stops: open/closed alignment; limit switch setpoints recorded.
- Packing/stem seal: check for visible leakage during cycles.
- Accessories: solenoids, regulators, positioners, air sets, feedback—wired and tagged per drawings.
Test Matrix (vertical template)
| Field | Value |
| Test | |
| Standard Ref | |
| Setpoint/DP | |
| Duration | |
| Media | |
| Instrument IDs | |
| Acceptance Ref | |
| Result |
Example — Shell Hydrostatic
| Field | Value |
| Test | Shell hydrostatic |
| Standard Ref | Per procedure (e.g., API 598) |
| Setpoint/DP | — |
| Duration | — |
| Media | Water |
| Instrument IDs | G-245, R-009 |
| Acceptance Ref | Per referenced clause |
| Result | Pass |
Example — Seat Leak (Both Seats)
| Field | Value |
| Test | Seat leak (both seats) |
| Standard Ref | Per procedure (e.g., ISO 5208) |
| Setpoint/DP | Category X |
| Duration | — |
| Media | Air |
| Instrument IDs | G-311 |
| Acceptance Ref | Per referenced clause |
| Result | Pass |
Example — Functional Stroke
| Field | Value |
| Test | Functional stroke |
| Standard Ref | Project spec §… |
| Setpoint/DP | N/A |
| Duration | N cycles |
| Media | — |
| Instrument IDs | — |
| Acceptance Ref | Per procedure §… |
| Result | Pass |
Always tie charts/readings to a unique valve tag/serial and keep gauge IDs visible in photos.
Common Nonconformities & How to Prevent Them
- Wrong end prep / face-to-face → Early dimensional verification against drawings.
- Seat damage / debris → Cleanliness check and protective caps before tests.
- Marking/nameplate mismatch → Visual & markings review before hydrotest.
- Incorrect leak test category → Cross-check procedure to PO/ITP and cited standard.
- Expired calibration → Calibration certificate screen before any testing.
- Traceability gaps → Heat/serial map completed during MTC/PMI step.
Preventive controls: FAT dry-run, standard-referenced procedures attached to ITP, labeled/dated gauges, and a single source-of-truth tag list.
Recording Results, Punch List & Release
- Record facts: measured values, clause references, instrument IDs, photo IDs.
- Punch list: log defects with owner/deadline; verify corrective action and re-test.
- NCR handling: contain, correct, verify; concessions only by buyer approval.
- Final dossier (example contents): signed valve inspection checklist (PDF), calibrated test charts, MTCs/CoC, NDE reports, photos, deviations/waivers, and release note—as required by the project spec.
FAQs — Valve Inspection & Testing
Which standard governs valve testing?
Use the one named in your PO/ITP (commonly API 598, ISO 5208, or EN 12266-1). Apply acceptance strictly per that reference.
How do I choose the seat leakage category?
Don’t choose ad-hoc. Follow the category specified by the procedure and project spec (e.g., as per API 598 or ISO 5208).
Do I need PMI and hardness on every valve?
Only if required by risk/service or the project. Acceptance criteria and extent are per the referenced standard/procedure.
What proves my gauges were valid?
Current calibration certificates mapped to instrument IDs used on the charts.
Can I accept minor visual defects?
Only if allowed by the referenced standard and they don’t affect function or pressure boundary; otherwise repair/rework and re-inspect.
What belongs on the nameplate?
Manufacturer, size/class, material, tag/serial, and other markings per drawing and the standard’s marking clauses.
Download: Valve Inspection Checklist (PDF)
Valve_Checklist.pdf
- Printer-friendly valve inspection checklist (docs → visual/dimensional → materials/PMI → NDE → hydrostatic & seat leak → functional).
- Acceptance placeholders that point to API 598 / ISO 5208 / EN 12266-1 as referenced by your project.
- Built-in tables for measurements, witness/hold points, punch list & disposition.
CTA: Download the Valve Inspection Checklist (PDF) and use it at your next FAT or incoming inspection.
Where to go next
- Select the right tightness framework: API 598 vs ISO 5208
- Understand test method differences: Hydrostatic vs Seat Leak Test
- Brush up on materials: MTC interpretation guide
Ready to upskill your team?
Join our hands-on course: Industrial Valve Inspection & Testing Training — practical leaks, procedures, and acceptance as per the standards your projects reference.